Residents in several communities across the Ashanti Region should expect scheduled power outages (dumsor)over six consecutive days as the Electricity Company of Ghana (ECG) undertakes work to improve electricity transmission.
The ECG, in a notice released on Saturday, November 21, announced that the outages would begin on Thursday, November 26, and continue until Tuesday, December 1, 2026.
According to the ECG, the planned interruptions will take place daily from 7:30 a.m. to 5:00 p.m. to allow the Ghana Grid Company Limited (GRIDCo) to upgrade the Anwomaso-Ridge Bulk Supply Point transmission line.
They further disclosed that the exercise will involve replacing the existing 364MVA single-circuit transmission line with a double-circuit system with a capacity of 2 x 488MVA, bringing the total transmission capacity to 976MVA.
The ECG further detailed that the project is intended to expand the capacity of the transmission network, strengthen electricity delivery and improve the reliability of power supply in the Ashanti Region.
The communities expected to be hit with the outages are Ahenema Kokoben, Sokoban, Daban, Asaago, Ampabame No. 1 and 2, Bekwame, Kotwi, Nkoransa, Paa, Kyekyewere, Pakyi No. 1 and 2, Brofoyedru, Sabin Akrofuom, Adum Afrancho and Anyinam.
Parts of Santase, Atonsu Kuwait, Naachia, Sawuah, Aprabon, Adagya, Esereso, Feyiase and Zoomlion, as well as neighbouring communities, will also be affected.
Meanwhile, the ECG has apologised to customers in the affected areas for the inconvenience the scheduled power interruptions may cause and appealed for their understanding as the upgrade is carried out.
In related news, some weeks ago, Mahama said Ghana is no longer experiencing power outages, popularly known as dumsor.
According to John Mahama, Ghana’s electricity supply has improved following his government’s efforts to settle debts owed to Independent Power Producers (IPPs), insisting that the country is currently not experiencing power outages.
Mahama disclosed that his administration had cleared outstanding debts owed to IPPs and introduced a payment arrangement to ensure that electricity suppliers are paid promptly for power supplied to the country.
Speaking to Ghanaians in Moscow, Russia, President Mahama explained that the measures had helped restore confidence among power producers, some of whom had previously threatened to suspend electricity supply because of unpaid bills.
He disclosed that the government inherited approximately $1.7 billion in debt owed to IPPs, alongside arrears for gas supplied from the Jubilee Field and by ENI.
According to him, addressing these financial obligations was critical to stabilising the energy sector and preventing potential disruptions to electricity supply.
Mahama stated, “With regards to energy, I can report that there’s no dumsor in Ghana. Everybody has adequate power. And that’s one of the areas that has been quite dramatic in terms of its management.
“I’m happy to announce that we have cleared the IPP debt. That is, we are current. Any energy they supply today, we’re paying them,” he said.
Mahama further explained that the government had established a payment plan to manage its remaining financial commitments, with initial payments followed by subsequent settlements as the obligations fall due.
He said the arrangement had improved the government’s relationship with power producers, who were now satisfied with the payment structure.
The President maintained that Ghana currently had enough electricity to meet demand, describing the changes in the management of the energy sector as significant.